LAI2-LAI3 Project

Long Acting Injectables project consisting of three project parts: LAI2, LAI3 and the new Utility Building

Scope

Scope handled

Design activities

  • Basic design
  • Detail design
  • IFC

Construction activities

  • Civil works (finishing works)
  • Cleanroom
  • Flooring
  • HVAC
  • Electrical installations (MV, LV, ELV)
  • New Chilled Water System
  • New Hot Water System
  • New Black Steam and Condensate System
  • New Potable Water & Drainage System
  • Clean media distribution and generation (WFI, PW, CS, N)
  • Automation (BMS and EMS/process automation)
  • Start-up and commissioning of all the systems and facility qualification