Flue gas desulphurization construction project for Nikola Tesla B (FGD TENT B) thermal power plant
Flue Gas Desulphurization Construction Project for Nikola Tesla B (FGD Tent B) Thermal Power Plant, 2x650MW (FGD TENT B), Mitsubishi Power
Scope
Scope handled
- Project Management of all project activities
- Mechanical scope, execution of mechanical works at a large scale industrial project
- Pre bid phase/process: presentation/introducing companies to local market, presentation of expected unit prices etc.
- Bid preparation process: complete support regarding Public Procurement Law.
- Design phase: monitoring complete designing process for PGD/PZI permits all in accordance with applicable Serbian legislation; design of some parts of plant
- Execution phase: monitoring and coordination of complete works; construction of absorbers, tanks, steel structure, flue gas ducts, pipe racks, piping (CS, SS, FRP), material conveyor system, installation of equipment
- QA/QC phase (establishing of procedures for obtaining of usage permit.
Key Features
- Desulphurization plant for major lignite powered power plant capacity 6x120MW
- Designed reduction of sulphur dioxide by 97%
- Two limestone slurry sprayed absorbers diameter 22m and height 34m
- Flue gas flow 2 x 3.000.000 Nm3/h
Project Highlights
In cooperation with technology owner (Mitsubishi Power) project successfully delivered through difficult period of corona pandemic, with minimum impact to timeline and cost.
Turnkey project delivered with zero claimed additional works.
DECO Pulse
Read more about this project
Comparable projects
Related projects
OngoingNon-renewable energy
Reconstruction and construction of the fire protection system
Pančevo Oil Refinery, NIS · Serbia · 2024-2027
DECO scope: Project & Construction Management, Equipment Procurement & Installation Services
CompletedNon-renewable energy
Flue gas desulphurization construction project for Nikola Tesla A (FGD TENT A) thermal power plant
Mitsubishi Power / EPS · Serbia · 2017 - 2024
DECO scope: Project & Construction Management
CompletedScience and technology
Construction of the Torlak BSL‑3 diagnostic & research facility
Ministry of Health, Serbia · Serbia · 2024 - 2025
DECO scope: Engineering & Design, Project & Construction Management, Equipment Procurement & Installation Services, Commissioning, Qualification & Validation
Planning something comparable?
Send us a project inquiry — the market is pre-selected. Drawings and documents go by e-mail.